Application of Dampproofing Material

(1)  Exterior dampproofing shall be applied from finished ground level to the top of the exterior of the footing.

    (2)  Unless otherwise stated in this Subsection, dampproofing shall be installed in accordance with the manufacturer’s instructions with regard to,

    (a)   surface priming,

    (b)   conditions during application,

    (c)   application quantity and rate, and

    (d)   curing times.

    (3)  Joints, cracks and penetrations shall be sealed to maintain the continuity of the dampproofing, where the dampproofing material is not capable of bridging such discontinuities.

Article 9.13.2.4 Ontario Regulation 332/12 Building Code,   Information published by oncodes.ca for educational purposes only.